  THE PROJECT INITIATION DOCUMENT
  One of the main outputs of the initiation stage should be the project initiation document, or PID. The term is poor because it implies that the PID is used only at the start of a project, when the project is being proposed, and ‘document’ might suggest a couple of pages only. In fact, the PID is of key importance both initially and throughout the duration of the project. It should address the following questions:
  · What should the project achieve? What are its deliverables? These should be specified in detail so that the project and its scope are well defined from the outset.
  · Why is the project is needed (including a cost benefit analysis)?
  · How will the quality or acceptability of outputs be assessed?
  · Who will lead the project?
  · Who will be on the project team and what will be the role and responsibility of each team member?
  · What are the risks? How have they been assessed and prioritised, and how will they be managed?
  · Who will carry out the work on the project? Which actions will be assigned to in-house staff and which to sub-contractors?
  · By when should the project and its various stages be completed?
  · What are the constraints on the project?
  · What are the assumptions on which the project depends?
  · How much budget has been allocated to the project?
  · What other resources are needed by the project, and have been allocated to it?
  · Who sponsors or owns the project?
  · What are the reporting arrangements?
  As this shows, the PID is the key reference document and it will be extensive and detailed, containing all the planning information required about the project.
 
  高顿网校小编寄语:人都是在跌倒与爬起之间学会坚强,都是在风雨与阳光之间走过成长的路。

   ACCA官方微信    
  扫一扫微信,*9时间获取2014年ACCA考试报名时间和考试时间提醒
  
  高顿网校特别提醒:已经报名2014年ACCA考试的考生可按照复习计划有效进行!另外,高顿网校2014年ACCA考试辅导高清课程已经开通,通过针对性地讲解、训练、答疑、模考,对学习过程进行全程跟踪、分析、指导,可以帮助考生全面提升备考效果。
  
  报考指南:2014年ACCA考试备考指南
  免费题库:2014年ACCA考试免费题库
  考前冲刺:ACCA备考秘籍
  高清网课:ACCA考试网络课程