以下是高顿网校小编为学员整理的:p3商务分析,供学员参考。
 
  FIGURE 5: NETWORK DIAGRAM / CRITICAL PATH ANALYSIS
  The numbers represent the time that each activity takes (let’s say in days). The project cannot proceed further until both content and layout have been decided. These are consecutive steps, one taking eight days and the next five days, so this small part of the project cannot be accomplished in less than 13 days. It does not matter that it takes only nine days to choose the ISP: everything has to wait for the content and design activities to be completed. These are critical activities, and if either
  were to take another day, completion of the whole project would be delayed by a day. Therefore, the project manager has to monitor critical activities very carefully. Choosing the ISP is a non-critical activity and it could be delayed by up to four days before impacting on project completion.
 
  Once project slippage is likely, the project manager has a number of choices, all of which should be discussed and perhaps negotiated with the project sponsor:
  · live with the slippage
  · reduce project scope
  · reduce project quality
  · bring in more resources, such as hiring sub-contractors to help out (which will, of course, increase costs)
  · move resources from non-critical to critical activities if skills are interchangeable.
  Even small projects can be broken down into many tasks, each with its own definition, personnel assigned, costs, start time, finish time and defined relationships with other tasks. Controlling this manually can be very arduous and project management software can be very useful in tracking each activity and, therefore, the progress of the project as a whole.
 
  高顿网校小编寄语:向着某一天终于要达到的那个终极目标迈步还不够,还要把每一步骤看成目标,使它作为步骤而起作用。

   ACCA官方微信    
  扫一扫微信,*9时间获取2014年ACCA考试报名时间和考试时间提醒
  
  高顿网校特别提醒:已经报名2014年ACCA考试的考生可按照复习计划有效进行!另外,高顿网校2014年ACCA考试辅导高清课程已经开通,通过针对性地讲解、训练、答疑、模考,对学习过程进行全程跟踪、分析、指导,可以帮助考生全面提升备考效果。
  
  报考指南:2014年ACCA考试备考指南
  免费题库:2014年ACCA考试免费题库
  考前冲刺:ACCA备考秘籍
  高清网课:ACCA考试网络课程