  FIGURE 4: THE CONTROL STAGE
  However, certain priorities or pressures are likely to apply to each variable, depending on the nature of the project. For example, a project involving safety-critical systems will rightly put great emphasis on quality because the consequence of technical failure will be very serious. However, managers need to be aware of the impact of the following compromises:
  · Increased emphasis on quality places the project in danger of taking longer and costing more.
  · Increased emphasis on meeting the cost budget may compromise quality, the project may take longer, or the scope could be narrowed.
  · Increased emphasis on meeting time deadlines may also compromise quality, cost over-runs are more likely (perhaps because overtime has to be paid), or scope could be narrowed.
  · If the emphasis is to ensure that the project scope is not reduced, then cost and time might increase, and quality might decrease. Naturally, if scope is increased, whether through project drift or through more pre-meditated changes to the project, costs, time and quality will all be severely jeopardised.
  None of these compromises is bound to happen, but project managers should be aware that such tensions exist and that a balance has to be maintained by management action, if necessary negotiating with the project sponsors to gain approval for changes.
  PROJECT PLANNING AND MANAGEMENT TOOLS
  Typically, projects consist of a number of separately identifiable steps which can be broken down, hierarchically, until manageable work packages are produced which can be assigned to the appropriate people. This is the process of deriving the work breakdown structure for the project. Each work package, or task, will have four components:
  · task name and description
  · costs, both marginal and any fixed element
  · duration
  · who is responsible and, in particular, whether the work will be carried out internally or externally.
  So now the project manager knows who is doing what and how much each element should cost. Using a relatively simple cost accounting system, material, labour, overheads and third party costs can be coded to the work packages, hence to the project, and actual costs can be compared to budget for control purposes.
  Still to be taken into account is the time that each work package will take, but whereas costs are cumulative, times need not be as often several tasks can be undertaken simultaneously. A more sophisticated approach is needed which sets out the relationship of the tasks or activities to one another, identifying those tasks which can be concurrent and those which can only be consecutive. For example, if the project was to set up a new website for the company, the task of choosing the internet service provider to host the website can be undertaken at the same time as designing the graphics and layout of the web pages. However, the layout and graphics couldn’t be finalised before the company has decided what information the web pages should show. These three tasks could be set out in a network diagram, or critical path analysis, as shown in Figure 5.
 
  高顿网校小编寄语:努力了,就无怨无悔。有道是:天道筹勤!相信自己,你是最棒的!

   ACCA官方微信    
  扫一扫微信,*9时间获取2014年ACCA考试报名时间和考试时间提醒
  
  高顿网校特别提醒:已经报名2014年ACCA考试的考生可按照复习计划有效进行!另外,高顿网校2014年ACCA考试辅导高清课程已经开通,通过针对性地讲解、训练、答疑、模考,对学习过程进行全程跟踪、分析、指导,可以帮助考生全面提升备考效果。
  
  报考指南:2014年ACCA考试备考指南
  免费题库:2014年ACCA考试免费题库
  考前冲刺:ACCA备考秘籍
  高清网课:ACCA考试网络课程