The cash flows as well as the NPV and IRR for the two projects are given. For both projects , the required rate of return is10 percent.![]() A. A rate between 0.00 percent and 10.00 percent. B. A rate between 10.00 percent and 15.02 percent. C. A rate between 15.02 percent and 16.37 percent. |