Frank is writing a briefing report on the phases of a project. In his explanation of the main phases, which two of the following would apply to the defining phase? A. The staff hours required are at their highest. B. Probability of successfully completing the project is very high. C. Risk and uncertainty are highest. D. Probability of successfully completing the project is lowest. E. The cost of making changes to the project is very high. |