Stone engaged Parker to perform personal services for $1,000 a month for a period of 3 months. The contract was entered into orally on August 1, year 1, and performance was to commence on January 1, year 2. On September 15, year 1, Parker anticipatorily repudiated the contract. As a result, Stone can A. Not assign her rights to damages under the contract to a third party. B. Immediately sue for breach of contract. C. Not enforce the contract against Parker since the contract is oral. D. Obtain specific performance. |