A company manufactures a single product, M. Budgeted production output of product M during August is 200 units. Each unit of product M requires 6 labour hours for completion and PR Co anticipates 20 per cent idle time. Labour is paid at a rate of $7 per hour. What is the direct labour cost budget for August? A. $6,720 B. $8,400 C. $10,080 D. $10,500 |