The managers of Rochester Manufacturing are discussing ways to allocate the cost of service departments such as Quality Control and Maintenance to the production departments. To aid them in this discussion, the controller has provided the following information: Assembly used QC 7,000 hours and machining used QC 21,000.the total cost of QC is $350000.Assembly used the maintenance department a total of 12,000 hours and machining used maintenance for 18,000 hours.the total cost of maintenance is $200000. If Rochester Manufacturing uses the direct method of allocating service department costs, the total service costs allocated to the assembly department would be A. $167,500. B. $80,000. C. $87,500. D. $120,000.
|