微信扫一扫
实时资讯全掌握
A factory assembles personal computers. During a period, 20,000 assemblies valued at $100,000 were transferred from process 1 to process 2. There was no opening WIP in process 2 for this period. During the period, $56,400 of additional cost was incurred in process 2. At the end of the period 18,000 units has been completed and 2,000 units were 40% complete. What is the cost of the closing work in process in process 2 (to the nearest $)?(2 marks) A $12,400 B $6,256 C $16,000 D $9,450 |