Which of the following statements is incorrect? A. Network diagrams are used to estimate project completion times, but not project resource requirements. B. PERT is a technique of project planning that includes an analysis of uncertainty in the duration of activities. C. In CPA, the critical path represents the minimum possible duration of the project. D. If tasks on the critical path are delayed, the project completion will be delayed by the same amount of time. E. In CPA, the critical path is the shortest sequence of consecutive activities through the network. |