Actual overheads
$496,980
Actual machine hours
16,566
Budgeted overheads
$475,200
Based on the data above, and assuming that the budgeted overhead absorption rate was $32 per hour, what were the budgeted number of hours (to the nearest hour) budgeted to be worked?
The correct answer is: 14,850.
The number of machine hours (to the nearest hour) budgeted to be worked were 14,850 hours.