| A materials or labor mix variance equals A. The actual total quantity of inputs times the difference between the weighted-average budgeted price for inputs and the weighted-average expected price for inputs. B. The actual total quantity of inputs times the difference between the weighted-average budgeted price for inputs and the weighted-average actual price for inputs. C. The budgeted total quantity of inputs times the difference between the weighted-average budgeted price for inputs and the weighted-average expected price for inputs. D. The actual total quantity of inputs times the difference between the weighted-average actual price for inputs and the weighted-average expected price for inputs. |