Bakker Industries sells three products (Products 611, 613, and 615) that it manufactures in a factory consisting of one department. Both labor and machine time are applied to the products. Bakker’s management is planning its production schedule for the next several months. There are labor shortages in the community. Some of the machines will be out of service for extensive overhauling. Available machine and labor time for each of the next 6 months is listed below. ![]() ![]() A. 400 units. B. 500 units. C. 800 units. D. 1,000 units. |