Football Contractors, Inc., which reports under U.S. GAAP, has contracted to build a stadium for the City of Washburn. The contract price is $100 million and costs are estimated at $60 million. Costs are not assured, however, because there is a material risk, which Football Contractors has assumed, that ground water problems might slow construction and increase costs by as much as $40 million. In 2004, the first year of the agreement, Football Contractors, Inc. billed $30 million, received a $20 million payment, and incurred $15 million in costs. For 2004 Football Contractors, Inc. should recognize revenue from the City of Washburn transaction in the amount of: A. $30 million. B. $20 million. C. $0. |