Leland Manufacturing uses 10 units of Part Number KJ37 each month in the production of radar equipment. The unit cost to manufacture 1 unit of KJ37 is presented below.
Direct materials $ 1,000
Materials handling (20% of direct material cost) 200
Direct labor 8,000
Manufacturing overhead (150% of direct labor) 12,000
Total manufacturing cost $21,200
Material handling represents the direct variable costs of the Receiving Department that are applied to direct materials and purchased components on the basis of their cost. This is a separate charge in addition to manufacturing overhead. Leland's annual manufacturing overhead budget is one-third variable and two-thirds fixed. Scott Supply, one of Leland's reliable vendors, has offered to supply Part Number KJ37 at a unit price of $15,000.
Assume that Leland Manufacturing does not wish to commit to a rental agreement but could use idle capacity to manufacture another product that would contribute $52,000 per month. If Leland elects to manufacture KJ37 in order to maintain quality control, Leland's opportunity cost is
A. $(20,000).
B. $4,000.
C. Some amount other than those given.