Ardmore Enterprises uses a standard cost system in its small appliance division. The standard cost of manufacturing one unit of Zeb is as follows: Materials - 60 pounds at $1.50 per pound $90 Labor - 3 hours at $12 per hour 36 Factory overhead - 3 hours at $8 per hour 24 Total standard cost per unit $150 The budgeted variable factory overhead rate is $3 per labor hour, and the budgeted fixed factory overhead is $27,000 per month. During May, Ardmore produced 1,650 units of Zeb compared with a normal capacity of 1,800 units. The actual cost per unit was as follows:
Materials (purchased and used) - 58 pounds at $1.65 per pound $95.70 Labor - 3.1 hours at $12 per hour 37.20 Factory overhead - $39,930 per 1,650 units 24.20 Total actual cost per unit $157.10
The flexible budget overhead variance for May is
A. $1,920 unfavorable. B. $3,270 favorable. C. $3,270 unfavorable. D. $1,920 favorable. |