The Kammel Building Company has a contract to build a building for $100 million. The estimate of the cost of the project is $75 million. In the first year of the project, Kammel had costs of $30 million. Kammel’s reported profit for the first year of the contract, using the completed contract method, is: A. $15 million. B. $0. C. $10 million. |