In accounting for long-term construction contracts, the percentage-of-completion method is preferable to the completed contract method when: A)estimates of the costs to complete and the extent of progress toward completion are reasonably dependable. B)the contracts are of a relatively short duration (less than one year). C)lack of dependable cost estimates cause forecasts to be doubtful. |