Choice "D" is correct. It occurs in the monitoring phase.
Choice "a" is incorrect. The baseline is developed during the planning process.
Choice "c" is incorrect. Project work activities are completed during the implementation process.
Choice "b" is incorrect. The baseline has not yet been defined in the authorization phase and thus cannot be compared.