Briar Co. signed a government construction contract providing for a formula price of actual cost plus 10%. In addition, Briar was to receive one-half of any savings resulting from the formula price’s being less than the target price of $2.2 million. Briar’s actual costs incurred were $1,920, How much should Briar receive from the contract? A. $2,060,000 B. $2,112,000 C. $2,156,000 D. $2,200,000 |