What is an auditor's evaluation of a statistical sample for attributes when a test of 50 documents results in 3 deviations if tolerable rate is 7%, the expected population deviation rate is 5%, and the allowance for sampling risk is 2%?
|
a. | Modify the planned assessed level of control risk because the sample deviation rate plus the allowance for sampling risk exceeds the tolerable rate. | |
b. | Modify the planned assessed level of control risk because the tolerable rate plus the allowance for sampling risk exceeds the expected population deviation rate. | |
c. | Accept the sample results as support for the planned assessed level of control risk because the sample deviation rate plus the allowance for sampling risk exceeds the tolerable rate. | |
d. | Accept the sample results as support for the planned assessed level of control risk because the tolerable rate less the allowance for sampling risk equals the expected population deviation rate. |
|