The controller for Durham Skates is reviewing the production cost report for July. An analysis of direct materials costs reflects an unfavorable flexible budget variance of $25. The plant manager believes this is excellent performance on a flexible budget for 5,000 units of direct materials. However, the production supervisor is not pleased with this result because he claims to have saved $1,200 in materials cost on actual production using 4,900 units of direct materials. The standard materials cost is $12 per unit. Actual materials used for the month amounted to $60,025. If the direct materials variance is investigated further, it will reflect a price variance of
A. Zero. B. $1,200 favorable. C. $1,225 unfavorable. D. $2,500 favorable.
|