William's project manager has convened a meeting to explain the characteristics of a typical project. After the meeting William's notes contain four main headings. Which set from the following would be most likely to explain the characteristics of a typical project? A. Start date, cost, schedule and quality. B. Start and finish dates, equipment ordered, schedule and quality. C. Cost, schedule, team members and quality. D. Start and finish dates, cost, schedule and quality. |