The standard labour rate per hour is $1. The standard time per unit of product A is 2 hours. The actual time worked was 40,000 hours but 42,000 hours were paid at a rate of $1.10 per hour. 19,000 units of product A were manufactured. Budgeted production was 20,000 units of product A. What is the labour rate variance? A. $4,000 (F) B. $4,200 (A) C. $4,000 (A) D. $4,200 (F) |