Aerosub, Inc., has developed a new product for spacecraft that includes the production of a complex part. The manufacture of this part requires a high degree of technical skill. Management believes there is a good opportunity for its technical force to learn and improve as they become accustomed to the production process. The production of the first unit requires 10,000 direct labor hours. Management projects an 80% learning curve and wants to produce a total of eight units.After completing the first unit, the estimated total direct labor hours Aerosub will require to produce the seven additional units will be After completing the first unit, the estimated total direct labor hours Aerosub will require to produce the seven additional units will be A. 30,960 hours. B. 40,960 hours. C. 56,000 hours. D. 70,000 hours. |